Global Leadership Development
Localisation Programme

WHAT MADE IT COMPLEX?
-
Programme included English development and a four-phase translation delivery plan.
-
Delivery involved high turnover, changing expectations and multiple departments.
-
Client reviewers and internal production teams needed a clearer process for multilingual asset delivery.
-
Budget visibility was limited because internal resource data and Oracle budget reporting were not linked.
my responsibility
-
Managed the four-phase translation programme after joining midway through English development.
-
Coordinated reviewers, translators, production teams and internal stakeholders.
-
Owned forecasting, budget tracking, resource planning and delivery governance.
-
Created trackers and process guidance to improve translation delivery control.
IMPACT
-
Improved profitability from -2% to 74%.
-
Created budget and resource trackers linking internal resource planning with Oracle budget tools.
-
Used daily reviews to identify where hours needed to be reallocated.
-
Created translation trackers and process guides that became the basis for other PMO tools later used across the EMEA PMO team.
LESSONS LEARNED
-
Commercial recovery depends on clear visibility of planned effort, actual effort and remaining scope.
-
Reviewer onboarding is essential in multilingual programmes because unclear review expectations create rework.
-
Lessons learned are most useful when applied during later phases, not only captured at the end.